Draw inspection basics.
What a draw inspection is, how it differs from other property evaluations, and the vocabulary of draw schedules and requests.
Do all construction loans require draw inspections?
No federal rule requires a draw inspection on every construction loan. The requirement comes from the lender's credit policy and loan agreement, and most loans disbursed in draws call for an inspection before each major draw. Credit union rules and the FHA 203(k) and HomeStyle programs add their own terms; small renovation loans may accept invoices or photos under policy.
Read the answerDoes a failed code inspection stop a construction draw?
Not by itself. A failed code inspection is the building department's rejection, requiring corrections and re-inspection before work continues. Whether a pending draw is funded is the lender's decision under its policy and loan documents. A draw inspection is a separate record that documents the work in place.
Read the answerHow do draws work on a Fannie Mae HomeStyle Renovation loan?
On a Fannie Mae HomeStyle Renovation loan, the renovation money goes into an escrow account at closing. The lender may release up to 50 percent of the planned renovation costs as an initial draw, then must get periodic inspections confirming the work matches the plans before each later draw. Completion is documented before the last funds are released.
Read the answerHow many draws are in a construction loan?
There is no fixed number. Residential construction loans commonly use somewhere between four and seven milestone draws, renovation programs often cap draws at five, and commercial projects typically draw monthly against a pay application. The loan agreement and the lender's policy set the schedule, not the borrower or the builder.
Read the answerIs a draw inspection the same as an appraisal?
No. An appraisal is a licensed opinion of value. A draw inspection is a verification of construction progress at a point in time. A construction loan usually needs both: the appraisal sets the as-completed value the loan is sized against, and draw inspections confirm that each funded stage of work is actually in place.
Read the answerWhat is a builder line of credit?
A builder line of credit is a revolving loan that funds a homebuilder's pipeline of houses rather than one house. A borrowing base caps what the lender will advance, based on each lot or house's type, value and stage, and the loan agreement limits how many unsold spec homes and models the line may carry at once.
Read the answerWhat is a construction draw inspection?
A construction draw inspection is a site visit, ordered by the lender, that verifies how much of the work claimed in a draw request has actually been completed. The inspector photographs the property, records percent complete by budget line item, and submits a report the lender uses to decide how much funding to release.
Read the answerWhat is a construction-to-permanent loan draw?
A construction-to-permanent loan draw is a release of building funds during the construction phase of a loan that later becomes a long-term mortgage. The lender pays in stages as inspected work is completed, and the borrower usually pays interest only on the amount drawn. When the home is finished, the loan converts to its permanent terms.
Read the answerWhat is a draw request?
A draw request is the borrower's or builder's formal application for a portion of construction loan funds, itemized against the approved budget and supported by evidence of progress. The lender reviews it, usually orders a draw inspection to verify the claimed work, and then funds all, part or none of the amount.
Read the answerWhat is a draw schedule?
A draw schedule is the pre-agreed plan that divides a construction loan into stages and says when funds are released as each stage is completed. It is set in the loan agreement, tied to the approved budget, and it tells the builder when to request money and the lender when to inspect.
Read the answerWhat is a progress inspection on a construction loan?
A progress inspection is a site visit that documents how far construction has advanced against the approved budget and schedule. When it is tied to a specific funding request it is called a draw inspection. Lenders also order progress inspections on a calendar, between draws, to catch stalled projects and keep the record current.
Read the answerWhat is retainage in construction lending?
Retainage is a percentage of each progress payment that is held back until the project is complete, usually released with the final payment once the work passes final inspection and final lien waivers are in. The construction contract sets the percentage, and some states regulate it by statute. A construction lender may also hold back part of each draw.
Read the answerWhat is the difference between a draw inspection and a building code inspection?
A building code inspection is made by the local building department to confirm permitted work meets the adopted code before it is covered or occupied. A draw inspection is ordered by the lender to confirm the work claimed in a draw request is in place. One protects the public; the other supports a funding decision.
Read the answerWhat is the difference between a draw inspection and a final inspection?
A draw inspection happens during construction and supports one funding request. A final inspection happens at completion and confirms the project is finished before the last draw is released. Neither is a municipal code inspection or a certificate of occupancy, and neither should be treated as one.
Read the answerWhat is the difference between a draw inspection and a home inspection?
A draw inspection verifies construction progress so a lender can fund a draw request. A home inspection evaluates the condition and function of a finished home for a buyer or owner. The draw inspector reports percent complete against the budget; the home inspector reports defects in systems and components. Different client, different question, different report.
Read the answerWhat is the difference between a draw inspection and a phase inspection?
A phase inspection checks the quality of a new home at set stages of construction, usually for the buyer or the builder. A draw inspection checks progress against the loan budget so the lender can fund a draw request. The two can visit the same house at the same stage and still answer different questions for different clients.
Read the answerWho performs draw inspections on an FHA 203(k) loan?
On a Standard 203(k) loan, a HUD-approved 203(k) Consultant inspects the work before each draw and signs HUD's draw request form; HUD requires a consultant on every Standard 203(k). A Limited 203(k) does not require a consultant, though one may be used, so the lender's own procedures decide how finished work is verified before funds go out.
Read the answer
Cost and pricing.
What draw inspections cost, who pays, how fees flow through closing, and why prices differ between vendors.
Can draw inspection fees be included in closing costs?
Often, yes. In residential programs, inspection costs may be incorporated into borrower closing costs, subject to lender policy and applicable requirements. For consumer-purpose construction loans the fee is a loan cost that has to be disclosed under Regulation Z, and how it is shown depends on whether it is collected at closing or later. Business-purpose loans follow the loan documents.
Read the answerHow much does a residential draw inspection cost?
A lender should expect a standard residential draw inspection fee of $100 to $300 per site visit, the typical U.S. range; rural or rush inspections often cost more. RAZE charges one flat $125 per single-family inspection at any U.S. address when RAZE sends the inspector, or $25 per request when your own inspector does the work.
Read the answerWho pays for a draw inspection?
The borrower usually pays for the draw inspection, as an expense of the construction loan, and the lender orders it. In residential programs, inspection costs may be incorporated into borrower closing costs, subject to lender policy and applicable requirements; they may also be netted from draw proceeds or billed per inspection. The loan agreement and fee schedule control.
Read the answerWhy do draw inspection prices vary by vendor?
Draw inspection prices vary because vendors are selling different amounts of work under the same name. Travel distance, the number of required photos and line items, quality review before delivery, turnaround expectations, inspector qualifications and the coordination overhead all move the price. Two quotes are only comparable once the scope is the same.
Read the answer
Process and timing.
How long inspections take, how often they are required, what inspectors look for, and what happens when the work falls short.
Are soft costs paid through construction draws?
They can be, when the loan budget includes them. Soft costs are non-construction project costs such as architecture, engineering, permits, legal fees, insurance and financing charges. A lender supports them with invoices, because a draw inspection documents work in place and cannot verify a soft cost. The loan agreement sets which ones are funded.
Read the answerCan a borrower do their own draw inspection?
Not as the lender's independent inspection, but often as a self-capture inspection the lender allows. Most lenders require an inspection ordered by the lender and performed by someone independent of the borrower. For lower-risk draws, some accept borrower or builder self-capture; on RAZE the lender sends it as a Direct Request completed in the RAZE Mobile App.
Read the answerCan a builder dispute a draw inspection report?
Yes. A builder or borrower disputes a draw inspection report through the lender, not the inspector, and supplies evidence: dated photos, invoices, delivery tickets or an approved change order. The lender decides whether the evidence is enough, whether to order a re-inspection and what to fund. The original report and any correction stay on the record.
Read the answerDoes the builder need to be present for a draw inspection?
Usually not. A builder or authorized contact needs to be there only when the site is locked, gated or unsafe to enter alone, or when the inspector needs questions about the work answered on the spot. What every inspection needs is safe, legal access, a contact who answers the phone and a current draw request.
Read the answerHow long does a draw inspection take?
A residential draw inspection usually takes about 15 to 45 minutes on site. The full turnaround, from the lender's order to a delivered report, also covers scheduling, travel, report preparation and review, and commonly runs from same day to several business days. RAZE averages 1.1 days from request to submission on residential draw inspections nationwide.
Read the answerHow long does it take to get a construction draw funded?
Many lenders fund a construction draw within a few business days of receiving a complete request, but there is no standard clock. Funding waits on the inspection report, lien waivers, title checks, documentation and the lender's own approval. The lender decides when and how much to release; the inspection company delivers the evidence.
Read the answerHow often are draw inspections required?
Most lenders order a draw inspection before each draw is funded. On loans that draw monthly, that works out to about one inspection a month. No federal rule sets a fixed schedule: the lender's credit policy and the loan agreement do. FDIC research on 28,939 construction loans found more frequent on-site inspections were associated with lower default rates.
Read the answerWhat does a draw inspector look for?
A draw inspector looks for evidence that the work in the draw request is in place: the right property, the construction stage reached, percent complete on each budget line, materials on site, and anything that conflicts with the request, such as stalled activity, unapproved changes or work covered before it was documented.
Read the answerWhat happens if a construction loan matures before the house is finished?
The loan documents decide. A loan that reaches maturity without payoff or conversion can be in maturity default, even if every payment was made on time. A lender may agree to extend the maturity; an extension fee is the charge for doing so. Before deciding, the lender checks how far the house is and what is left to build.
Read the answerWhat happens if a draw inspection shows less work than requested?
The lender decides. Common outcomes are funding only what the documented work supports, holding the draw until the work catches up, or asking the borrower to revise the request. The inspector's job is to document the gap with line-item percentages and photos; the funding decision and any follow-up belong to the lender.
Read the answerWhat is a remote draw inspection?
A remote draw inspection verifies construction progress without an inspector on site, using photos or live video captured at the property and reviewed by the lender or an inspector elsewhere. Lenders use it for selected lower-risk draws; it does not replace an on-site visit when independent physical observation is required.
Read the answerWhat is a self-inspection draw?
A self-inspection draw is a construction draw supported by photos or video the borrower or builder captures instead of an independent inspector's visit. Lenders use it where it fits the risk: smaller draws, simple scopes or experienced borrowers. On RAZE, the lender sends a self-inspection as a Direct Request that the borrower or builder completes in the RAZE Mobile App.
Read the answerWho gets paid from a construction draw?
It depends on the disbursement method in the loan agreement. A lender may pay the borrower, who then pays the builder; issue a check payable jointly to the borrower and the contractor; or have a third party pay contractors and suppliers directly. The lender chooses the method, and the inspection comes first.
Read the answer
Reports and evidence.
What a draw inspection report contains, photo requirements, percent complete, stored materials and record retention.
How are stored materials verified?
Stored materials are verified with paperwork and a site check. Lenders typically ask for the invoice or bill of sale, proof the borrower or contractor owns the materials, insurance that covers them where they sit, and photos showing them on site, protected and matching the invoice. Off-site storage usually adds a storage agreement and an inspection at that location.
Read the answerWhat are stored materials in a construction draw?
Stored materials are building materials bought or delivered for the project but not yet installed, such as windows on site or cabinets in a warehouse. Some lenders fund them in a draw before installation, when the loan agreement allows it and the materials are verified, secured, insured and owned by the borrower or contractor. Others fund installed work only.
Read the answerWhat is included in a draw inspection report?
A draw inspection report should include, and typically does, the property and project identifiers, the inspection date, photographs, percent complete by budget line item, the inspector's comments and any exceptions, such as stalled work or items that don't match the request. Many lenders also require stored materials, site conditions and answers to their own questions.
Read the answerWhat is percent complete in a draw inspection?
Percent complete is the inspector's assessment of how much of each budget line item is finished, based on the physical work visible on site rather than time elapsed or money spent. The lender compares those percentages with the draw request to work out how much of each line the documented work supports.
Read the answerWhat photos are required for a draw inspection?
There is no universal photo list; the lender's inspection criteria set the requirements. Most lenders ask for the address or front elevation, every side of the structure, the work behind each funded budget line, stored materials and any exception, with enough photos to support every percent-complete figure in the report.
Read the answer
Software and workflow.
Draw inspection software, ordering engines, inspector portals, mobile capture and how the inspection layer fits beside loan administration.
Are actions taken through an AI assistant logged in RAZE?
Yes. Actions taken through the RAZE MCP are logged in RAZE. An order placed from an assistant creates the same inspection record as an order placed in the Ordering Engine or by API, with the same history of status changes and who made them.
Read the answerCan an AI assistant order a draw inspection without asking me?
By default, no. The RAZE MCP shows a summary and waits for your confirmation before it creates or changes anything. A user can tell the assistant to skip that step. Most lenders will want a simple team rule: keep confirmation on for anything that creates or changes a record.
Read the answerHow can a lender order draw inspections with an MCP server?
A lender connects an MCP-compatible AI assistant or agent to the RAZE MCP server, each person signing in with their own RAZE account. The team names the project and address, the assistant collects the order details and shows a summary, and by default a person confirms before the order is placed on the Marketplace or as a Direct Request.
Read the answerWhat controls should a lender set before connecting an AI assistant to a vendor?
Common controls are simple. Decide which assistants your team may connect. Give each user the RAZE role the job needs and no more. Keep confirmation on for anything that creates or changes a record. Limit who can add connectors. Have a reviewer check summaries against the report.
Read the answerWhat does "AI-native" mean in lending software?
"AI-native" describes software built around artificial intelligence as a core function, rather than an existing application with AI features added. There is no standard definition. The label describes architecture, not security or data handling, and it does not say who approves what the AI produces, so a lender should ask before granting access.
Read the answerWhat is an inspector portal?
An inspector portal is the web workspace an inspection vendor uses to run its side of the work: receiving assigned jobs, completing the lender's draw sheet and questions, attaching photos, submitting reports and managing its inspectors. The lender orders and reviews in its own system; the portal is where the vendor's team does the work in between.
Read the answerWhat is construction loan management software?
Construction loan management software is the system a lender uses to run a construction loan after closing: the budget, draw requests, approvals, documents and disbursements. Lenders also call it construction loan administration (CLA) software. It does not visit the site. Draw inspections are a separate layer that connects to it, which is where RAZE fits.
Read the answerWhat is the difference between the RAZE API and the RAZE MCP for a lender?
The RAZE API is for developers who connect a loan system to RAZE. The RAZE MCP offers the same API to an AI assistant, so a person can ask in plain language. Both reach the same RAZE data with the user's own permissions, and both work beside your LOS and core.
Read the answerWhat is the RAZE MCP?
The RAZE MCP is the RAZE API offered as a Model Context Protocol server for MCP-compatible AI assistants and agents. Your team can order inspections and create projects, check status and history, pull reports, photos and questionnaire answers, and review capture metadata down to the data behind every photo.
Read the answerWhich AI assistants work with the RAZE MCP?
The RAZE MCP works with MCP-compatible AI assistants and agents. RAZE has tested it with Claude, Claude Code, ChatGPT, Cursor and Microsoft Copilot (as of November 2026). Other MCP-compatible assistants can connect, though RAZE has not tested each one. Some business plans need an administrator to allow custom connectors first.
Read the answer
Marketplace and Direct Request.
Where to get a draw inspector at any U.S. address, managed fulfillment, lender-performed inspections, and how one standard covers both.
How should a lender choose a draw inspection company?
Choose on evidence you can check before the first order: coverage for every address in your book, qualified inspectors independent of your loan staff, a sample report detailed enough to support a disbursement, published pricing, turnaround stated as a measured average, and whether your own inspectors can work on the same report. Then confirm how orders move through your systems.
Read the answerWhere do I get a draw inspector?
Lenders get draw inspectors from an in-house team or vendor panel, a local independent inspector, or a draw inspection company with a network. Through RAZE, a lender can order one at any U.S. address, including Alaska and Hawaii: a flat $125 per single-family inspection when RAZE sends the inspector, or $25 per request with the lender's own inspector.
Read the answerWho is the best draw inspector for banks?
For a bank, the best draw inspector meets what examiners check: qualified, independent of the lending function, and reporting in writing before each advance, at every address in the loan book. Our pick for banks is RAZE, which publishes this answer: the bank's own inspectors and the RAZE Inspection Network on one report standard, at any U.S. address.
Read the answerWho is the best draw inspector for credit unions?
For a credit union, the best draw inspector gives a lean lending team an independent, written report before each advance, at any address a member builds on. Our pick for credit unions is RAZE, which publishes this answer: the credit union's own inspectors and the RAZE Inspection Network on one report standard, ordered and tracked in one place.
Read the answer
Audit and compliance.
Audit trails, chain of evidence, examiner expectations and the limits of what software can promise.
Do draw inspections reduce construction loan defaults?
Yes, on one bank's book. The FDIC working paper by Heitz, Martin and Ufier studied 28,939 multiple-draw construction loans: loans with more on-site inspections were less likely to default, and in their estimate roughly two to three inspections per 100 days lowered the default probability by 3.64 percentage points. Inspections are a monitoring control, not a safeguard against every loss.
Read the answerDoes draw inspection software guarantee compliance?
No. Draw inspection software can support a lender's compliance program, but it cannot make the lender compliant. Compliance rests on the lender's written policy, the people who apply it and the review behind each advance. Software helps by capturing the same evidence on every order and keeping a dated record of who did what, which supports audit and exam review.
Read the answerHow do examiners review construction loan monitoring?
Examiners test whether a lender's controls match its construction lending. The FDIC's procedures ask whether inspectors are qualified and independent of lending, whether reports support disbursements, whether funds go out only after written inspection reports, lien searches and title updates are reviewed, and whether lien waivers and a certificate of occupancy precede final disbursement.
Read the answerWhat is a lien waiver and when is it required for a draw?
A lien waiver is a signed release in which a contractor, subcontractor or supplier gives up the right to file a mechanics' lien for work it has been paid for. Lenders commonly collect waivers with each draw for prior payments, and final waivers before the last draw. The loan agreement and state law set the requirements; confirm them with counsel.
Read the answerWhat is a title update on a construction draw?
A title update, also called a date-down, searches the public record from the date the lender's title coverage last reached to the day of a new advance. It shows whether a lien, judgment or other claim was recorded against the property since the last draw, so the title insurer can extend the lender's coverage to the new money.
Read the answerWhat is chain of evidence in construction lending?
In construction lending, chain of evidence is the unbroken link between what an inspector saw on site and the lender's decision to fund a draw. It rests on evidence captured at the source, with date, time and location metadata, kept in its original form, and a record of who handled it and when, from the field visit to the disbursement.
Read the answerWhy do email-based draw workflows create audit issues?
Email moves files but keeps no single record of a draw. Reports and photos scatter across inboxes, versions multiply, forwarded photos can lose their metadata and their link to budget lines, and approvals sit in reply threads. When an auditor or examiner asks who approved which draw, when and on what evidence, someone has to piece the answer back together.
Read the answer
Private and rehab lending.
Fix-and-flip draws, rehab inspections and ordering a single inspection without a platform rollout.
Are hard money rehab draws paid after the work is done?
Most hard money and fix-and-flip lenders pay rehab draws after the work is done. The borrower pays for a phase of work, requests a draw, and the lender reimburses it once an inspection documents the work in place. Some lenders advance part of the first draw or fund materials deposits. The loan agreement sets the terms.
Read the answerHow do fix-and-flip lenders manage draws?
Fix-and-flip lenders typically approve a line-item rehab budget at closing, hold it back, and release it in draws. For each draw, the borrower requests funds, an inspection documents the work in place, and the lender reviews the report before funding what it supports. The loan agreement sets the number of draws, the fees and the evidence required.
Read the answerWhat is a construction holdback?
A construction holdback is loan money the lender keeps back at closing and releases in stages as the work is done. On a rehab or fix-and-flip loan, the holdback is usually the renovation budget, paid out through inspected draws. The term is also used for retainage, a percentage withheld from each payment until the project is complete.
Read the answerWhat is a rehab draw inspection?
A rehab draw inspection is a site visit that documents progress on a renovation before the lender releases the next draw. The work happens inside a house that already stands, so the inspector measures each scope-of-work line, separates new work from what was already there, and records demolition, hidden conditions and scope changes.
Read the answerWho is the best draw inspector for private lenders?
For a private lender, the best draw inspector protects each reimbursement: an independent inspector, photos tied to the budget lines and a prompt report, in any market the lender funds. Our pick for private lenders is RAZE, which publishes this answer: published rates at any U.S. address, with the lender's own inspectors or the RAZE Inspection Network.
Read the answer
For inspectors.
Becoming a draw inspector, pay, equipment and how assignments are offered.
Do draw inspectors need a license?
There is no single nationwide draw-inspector license. Requirements vary by state, by lender and by the scope of the work; some lenders or inspection companies ask for a home-inspector license, a certification, a background check or insurance. RAZE screens every inspector to its published standards, and a lender's own requirements apply on top of them.
Read the answerHow are draw inspection assignments offered to inspectors?
On RAZE, Marketplace inspections appear in the RAZE Mobile App for qualified inspectors, each with its distance in miles. The inspector opens the job, reads the due date, draw number, fee and Special Instructions, and taps Lock Inspection to take it. Direct Request work comes from a lender who already works with the inspector, through the same app and report.
Read the answerHow do I become a draw inspector?
Start from work that already reads a job site: construction, home inspection, appraisal, insurance adjusting or project management. Learn the job: documenting percent complete for each budget line with time- and location-stamped photos. Then apply to the RAZE Inspection Network, which verifies identity, tests competency, screens watchlists and keeps insurance on file before any assignment is visible.
Read the answerHow much do draw inspectors get paid?
Draw inspectors are paid per inspection, and the fee varies by provider, region, travel and job type. RAZE pays its inspector network $60 to $85 per standard single-family draw inspection, more for duplexes to quadplexes and up to $250 on rare jobs. Inspections submitted Sunday through Saturday are direct deposited the following Friday, with nothing to invoice.
Read the answerWhat equipment does a draw inspector need?
A smartphone or tablet running the RAZE Mobile App on iOS or Android, a charger, reliable transportation, internet access and PPE: a hard hat, a safety vest and protective footwear. Add a tape measure where the draw sheet calls for measurements. The app captures the photos with time and location stamps, so no separate camera is needed for RAZE work.