Back to Blog
LendersDraw InspectionsConstruction Loans

Permits, Code Inspections and Construction Draws

ByRAZE Team
•November 18, 2026•5 min read
Permits, Code Inspections and Construction Draws

The framing passed its code inspection on Tuesday. On Thursday the builder sends a draw request for the framing line. The two events sound like the same fact. They are two different records, made by two different inspectors for two different readers.

The comparison has its own page: draw inspection vs. building code inspection. This guide covers the permit events a lender may see during a build and what belongs in the draw file for each. Local rules govern permits and inspections; nothing here is legal advice.

The building department's record

A building permit is the primary permit authorizing construction of a structure per approved plans. Building inspections are the municipal inspections at code-required stages, such as footing, framing, rough MEP and final, that authorize work to proceed. The permit holder calls for each one, and work that fails is corrected before it is covered.

Those records answer whether the work met the code. A draw inspection answers a different question: whether the work claimed in the draw request is in place.

Four permit events and the draw file

Failed inspectionWhat it isAn inspector's rejection requiring corrections and re-inspection before work continuesWhat the draw file can holdThe notice, and the draw report for the same stage
Stop work orderWhat it isAn official order halting construction due to violations, permit issues or safety hazardsWhat the draw file can holdThe order, and an inspection that records the site as it stands
Temporary certificate of occupancyWhat it isConditional permission to occupy while minor items are completedWhat the draw file can holdThe certificate, and the items still open
Certificate of occupancyWhat it isThe government certificate confirming a building complies with codes and may be occupiedWhat the draw file can holdThe certificate, with the final draw inspection

What to write into the draw policy

  1. Say which permit records the file needs

    Name the permit documents the lender wants to see and when, such as the building permit before the first draw and the certificate of occupancy at the final draw.

  2. Keep the two inspections apart

    A passed code inspection is not a draw inspection. Say in policy that a draw is supported by the lender's own report of work in place, whatever the building department's record shows.

  3. Decide what a failed inspection or a stop work order means

    Say whether the lender wants to be told, who reviews it and what happens to a pending draw. That decision belongs to the lender and its loan documents.

  4. Record the site when work stops

    When construction halts, an inspection of the site as it stands gives every later decision a baseline. The stalled loan guide covers what to record.

A draw inspection is not a code inspection.

The building department decides whether work meets the code. A draw inspector documents how far the work has progressed. Neither record replaces the other.

Where RAZE fits

RAZE runs the lender's side. The lender sets the required questions and photos on each order in the Ordering Engine, the inspector completes them in the RAZE Mobile App, and every report carries GPS and time-stamped photos linked to the draw sheet line items they support.

RAZE does not perform code inspections or issue permits; the lender decides what funds.

Frequently asked questions

It is an official order halting construction due to violations, permit issues or safety hazards. What it means for a pending draw is set by the lender's policy and the loan documents.

Only where the lender's order asks for it, such as a photo of the posted permit. A draw inspection documents work in place for the lender. It does not confirm code compliance; the building department does.

It is conditional permission to occupy a building while minor items are completed. The full certificate of occupancy confirms the building complies with codes and may be occupied.

Keep reading

The lender's own record of the work

See progress by line item, with photos tied to each line.

For Lenders

See a draw inspection on a project in your book, from order to delivered report.

Get Started

The Short Questions

How reports handle photos, percent complete and draw sheet lines.

Read the FAQs

The building department checks the code.The lender checks the work in place.