Foundation Draw Inspection: Before the Pour

ByRAZE Team
•November 20, 2026•5 min read
Foundation Draw Inspection: Before the Pour

By the time the slab is finished, much of the work this draw paid for is under it: the footings, the steel, the membrane and the soil treatment. A report taken after the pour shows the slab. It cannot show what is inside it.

This guide lists the foundation terms a draw desk meets and what a draw record can show before and after the pour. A draw inspection is not a structural or code inspection. The building department and the engineer decide compliance.

Eight terms at the foundation

FootingsWhat it isBelow-grade concrete bases that spread the structure's load to the soil and anchor the foundationVisible after the pour?No; below grade
Slab-on-gradeWhat it isA reinforced concrete floor poured directly on prepared ground, serving as both foundation and floorVisible after the pour?Yes; it is the visible surface
Monolithic slabWhat it isA slab and thickened-edge footings poured in a single placementVisible after the pour?The edges only
Stem wallWhat it isA short foundation wall rising from the footing to support the floor structure above gradeVisible after the pour?Yes; above grade
RebarWhat it isSteel reinforcing bars embedded in concrete to provide tensile strengthVisible after the pour?No; embedded
Vapor barrierWhat it isA plastic membrane under the slab blocking ground moisture from migrating into the buildingVisible after the pour?No; under the slab
Termite treatment (pre-treat)What it isSoil treatment applied before the slab pour to prevent subterranean termite intrusionVisible after the pour?No; applied to the soil
Form board surveyWhat it isA survey verifying foundation forms are correctly placed within setbacks before concrete is pouredVisible after the pour?It is a document, not a photo

Four of the eight are hidden once the slab is poured, and a monolithic slab's footings show only at the edges. The glossary notes that termite pre-treat is required in many southern jurisdictions and that slab-on-grade is standard in Florida, so this draw carries more hidden work in some markets than in others.

Two visits, two records

  1. Before the pour

    Forms are set, the steel is in, the membrane is down and the ground is treated. A visit now photographs work that will not be visible again. Whether to order one is the lender's policy call.

  2. The survey in the file

    The form board survey verifies the forms sit within setbacks before concrete is poured. It comes from a surveyor; the draw file holds it beside the inspection when the policy requires it.

  3. After the pour

    The ordinary foundation draw visit happens after the slab is poured and before framing starts. The draw inspection checklist covers what that visit shows and when to hold the draw.

  4. Before the next draw

    Framing covers the slab edges and plumbing stub-ups. Anything the policy wants on record from the foundation stage belongs in the file before the framing draw funds.

This is not a structural or code inspection.

A draw inspection documents visible work in place. It does not test concrete, check rebar spacing or certify code compliance. The building department and the engineer decide compliance.

Where the code inspection fits

Under Section R109 of the International Code Council's 2021 International Residential Code, the inspections a building official makes on a permitted home include the foundation, and work that fails is corrected before it is covered. Cities and counties adopt the code with their own amendments, so the list varies by place and edition. That inspection belongs to the city or county, and its result is a separate record. The permits and code inspections guide covers how the two sit side by side, and the short answer on a draw inspection versus a building code inspection covers who checks what.

Where RAZE fits

RAZE documents the work; the lender decides what to fund. A RAZE report shows percent complete by draw sheet line, and the lender's policy decides which visits to order.

Each photo carries GPS coordinates and date and time stamps and is linked to the draw sheet line it supports, so a pre-pour photo shows when the steel and membrane were in place. RAZE does not approve, deny or fund draws.

Frequently asked questions

It is a slab and thickened-edge footings poured in a single placement.

It is a survey verifying foundation forms are correctly placed within setbacks before concrete is poured.

It is a plastic membrane under the slab blocking ground moisture from migrating into the building.

Keep reading

A dated record before the concrete

See progress by line item, with photos tied to each line.

For Lenders

See a draw inspection on a project in your book, from order to delivered report.

Get Started

The Short Questions

How reports handle photos, percent complete and draw sheet lines.

Read the FAQs

The slab covers the work.The record keeps it.