Site Work & Pad
- Pad cleared, filled, and at grade
- Silt fence / erosion control in place
- Permit posted and NOC recorded

This page is built for draw inspectors and construction lending teams, whether you are learning what a draw inspection is or verifying your hundredth dry-in. Start on the house below, walk the 7-stage field guide, then look up any term in the Construction Lending Glossary.
Build stages
Tappable house points
Core terms
Eleven components in build order, the sequence a draw schedule follows from foundation to roof, each one tap from its definition.
Below-grade concrete bases that spread the structure's load to the soil and anchor the foundation.
Read it in the glossary →The vocabulary every draw decision runs on, each term one tap from its definition in the glossary.
The seven broad stages of a residential build, illustrated, with the checkpoints an inspector confirms at each visit.
Important: Draw schedules vary. Some lenders fund four draws, others eight or more; line-item schedules don't map one-to-one to stages, and stages can overlap or be combined. The stage numbers below describe the sequence of construction — the loan agreement's draw schedule always controls what each draw funds.
The RAZE Construction Lending Glossary defines 506 draw inspection, loan administration and building terms, each one tap away.
The borrower / builder submits the draw request to start the cycle.
The ordering engine routes the inspection request.
Field visit with geo-stamped photos — the control point between the request and the money.
Percent complete is verified against the budget and plans.
Loan balancing and approval before funds move.
Disbursement closes the cycle and feeds the audit trail.
Clear and grade — inspection covers permits and pad.
Footings and slab — inspection confirms slab poured.
Walls and trusses — inspection confirms frame complete.
Roof and windows — inspection confirms the house is weathertight.
Electric, plumbing, HVAC — inspection confirms rough-ins passed.
Drywall and trim — inspection confirms interior finished.
Punch list and occupancy — final draw gated by CO and lien waivers.
One common pattern: an inspection verifying each phase before the draw that funds it. The number of draws and which phases they cover vary by lender, program, and loan agreement.
A draw inspection is a site visit that verifies construction progress before a lender releases the next portion of a construction loan. The inspector documents what is actually built — usually with dated, geo-stamped photos and a percent-complete assessment against the budget — so the lender has documented evidence of work in place before funding.
The inspector confirms the work claimed in the draw request is complete: the right stage is finished (slab, framing, dry-in, rough-ins, finishes), the work matches the plans and budget line items, and there are no red flags like stalled activity, missing materials, or work covered up before verification. The report typically includes photos of each side of the structure and each funded line item.
Residential draw inspections commonly run in the range of roughly $100 to $300 per visit depending on the market, travel distance, and report requirements, and the fee is usually passed through to the borrower. Rural or hard-to-cover areas tend to price higher because inspector coverage is thinner. RAZE charges a flat $125 per single-family inspection at any U.S. address, or $25 per request with your own inspector (getaraze.com/pricing).
The site visit itself usually takes 15 to 45 minutes for a residential project. What matters more to builders is turn time — the elapsed time from the draw request to the delivered report — which ranges from same-day to several business days depending on the inspection provider and coverage in the area.
Most residential construction loans use 5 to 8 draws tied to milestones such as slab, frame, dry-in, rough-ins, finishes, and final. The exact schedule is set in the loan agreement, and each draw is typically conditioned on a passing inspection of the prior stage.
Draw inspections are performed by third-party inspection firms, independent field inspectors, appraisers, or in some cases the lender's own staff. Lenders increasingly use managed inspection networks so they can get consistent, geo-stamped reports in every market where they lend.
Most draw inspectors come from construction, appraisal, insurance adjusting, or home inspection backgrounds, and requirements vary by state and by the firm you work with. The core skills are recognizing the stages of construction, photographing a site thoroughly, and completing a percent-complete report accurately — the field guide and glossary on this page cover the vocabulary you will use every day.
A home inspection evaluates the condition and defects of a completed home for a buyer. A draw inspection verifies construction progress for a lender — it answers "is the work funded actually built?" not "is this house in good condition?" Draw inspections are shorter, repeat at each milestone, and report percent complete rather than deficiencies.
Open the Construction Lending Glossary
Every draw inspection, loan administration and building term in one searchable reference, with full pages for the terms lenders look up most.
Explore the RAZE Blog
Guides, checklists, and training resources for draw inspectors and construction lending teams — from first site visit to full portfolio management.
See a Sample RAZE Inspection Report
Geo-stamped photos, line-item percent complete, and an audit trail your examiners will actually like.
RAZE turns draw inspections into photo-documented reports built to support audit and exam review, so every stage on this page shows up correctly in your loan file.